Tämä on FBI:n tutkinta-asiakirja Epstein Files -aineistosta (FBI VOL00009). Teksti on purettu koneellisesti alkuperäisestä PDF-tiedostosta. Hae lisää asiakirjoja →
FBI VOL00009
EFTA00797875
Sivut 1–20 / 27
Sivu 1 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999) Keyeite Yellow Flag - Negative Treatment Distinguished by Gengler v. U.S. ex rel. its Dept. of Defense and Navy. E.D.Cal.. August 24.2006 F.3d 1368 United States Court of Appeals, Federal Circuit. AMERICAN TELEPHONE AND TELEGRAPH COMPANY, and Lucent Technologies Inc., Plaintiffs—Appellants, v. UNITED STATES, Defendant/Cross—Appellant. Nos. 95- 5153, 95- 5154. May 26, 1999. Synopsis Contractor sued Government under Contract Disputes Act for recovery of expenditures under research and development contract. The Court of Federal Claims, John P. Wiese, J., 32 Fed.CI. 672, ruled that contract was void and that quantum meruit relief was available, but certified questions for interlocutory appeal. The Court of Appeals originally affirmed, but, on rehearing en banc, the Court of Appeals, Pauline Newman, Circuit Judge, held that: (1) Navy contracts for development of ship-towed, undersea surveillance system was for "major system or subsystem," for purposes of statute prohibiting Department of Defense from entering into fixed price contracts for development of major system or subsystem exceeding $10 million unless certain conditions were met, and (2) Department's failure to comply with statute's requirements did not render contract void ab initio. Questions answered and case remanded. Rader, Circuit Judge, concurred in the result and filed opinion in which Mayer, Chief Judge, and Lourie, Circuit Judge, joined. Plager, Circuit Judge, dissented in part, concurred in part, and filed opinion. Opinion, 124 F.3d 1471, vacated. West Headnotes (5) Ill Public Contracts • Compensation United States • Compensation Navy contract for development of ship-towed. undersea surveillance system was for "major system or subsystem," for purposes of statute prohibiting Department of Defense from entering into fixed price contracts for development of major system or subsystem exceeding $10 million unless certain conditions were met, notwithstanding either WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 1 EFTA00797875
Sivu 2 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999) agency's reliance on separate statute to define major system as having $75 million floor or fact that contract was funded over multiple years. 10 U.S.C.A. § 2302(5); Act December 22, 1987, § 101(b), Sec. 8118, 101 Stat. 1329. 9 Cases that cite this headnote 121 Administrative Law and Procedure e- Erroneous or unreasonable construction; conflict with statute Although an agency's interpretation of a statute it administers is indeed entitled to deference, agency discretion does not extend to changing a clearly stated dollar figure. Cases that cite this headnote 131 Public Contracts 1— Compensation United States Compensation Failure of of Defense with statute Department to comply setting forth internal review and reporting requirements for fixed price contract for development of major system or subsystem exceeding $10 million did not render such contract void ab initio, as statute itself did not announce sanction of contract invalidity, and contract had been fully performed. Act December 22, 1987, § 101(b), Sec. 8118, 101 Stat. 1329. 24 Cases that cite this headnote 141 Public Contracts offr. Unauthorized or Illegal Contracts United States o- Unauthorized or Illegal Contracts Invalidation of government contract is not a necessary consequence when a statute or regulation has been contravened, but must be considered in light of the statutory or regulatory purpose, with recognition of the strong policy of supporting the integrity of contracts made by and with the United States. 13 Cases that cite this headnote 151 Contracts o- Nature and Essentials in General The invalidation of a contract after it has been fully performed is not favored. WESTLAW 2019 Thomson Reuters. No claim to original U.S. Government Works. 2 EFTA00797876
Sivu 3 / 27
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999) 11 Cases that cite this headnote Attorneys and Law Firms *1369 C. Stanley Dees, McKenna & Cueno, L.L.P., of Washington, DC, argued for plaintiffs-appellants. With him on the brief was J. Keith Burt. Of counsel on the brief were Thomas R. Suher, and Dean L. Grayson, Lucent Technologies, Inc., of Washington, DC. Bryant G. Snee, Assistant Director, Commercial Litigation Branch, Civil Division, Department of Justice, of Washington, DC, argued for defendant-cross appellants. With him on the brief was David M. Cohen, Director. Of counsel on the brief were Robert D. Hogue, James H. Haag, Attorneys, Office of General Counsel, Department of the Navy, of Arlington, Virginia. Caryl A. Potter, III, Sonnenschein Nath & Rosenthal, of Washington, DC, for amicus curiae Electronic Industries Alliance and Aerospace Industries Association of America, Inc. With him on the brief were Elizabeth A. Ferrell, of Washington, DC; Alan M. Posner, of Chicago, Illinois; and Roger K. Heidenreich, of St. Louis, Missouri. John Lloyd Rice, Miller & Chevalier, Chartered, of Washington, DC, for amicus curiae Federal Circuit Bar Association. With him on the brief was Clarence T. Kipps, Jr. Of counsel on the brief were L. James D'Agostino, Reed Smith Shaw & McClay, of McLean, Virginia; and George Hutchinson, Executive Director, Federal Circuit Bar Association, of Washington, DC. Before MAYER, Chief Judge, NEWMAN, PLAGER, LOURIE, CLEVENGER, RADER, SCHALL, BRYSON, and GAJARSA, Circuit Judges. * Opinion Opinion for the court filed by Circuit Judge NEWMAN, in which Circuit Judges CLEVENGER, SCHALL, BRYSON, and GAJARSA join. Opinion concurring in result filed by Circuit Judge RADER, in which Chief Judge MAYER and Circuit Judge LOURIE join. Opinion dissenting-in- part and concurring-in-part filed by Circuit Judge PLAGER. NEWMAN, Circuit Judge. We took this appeal and cross-appeal en banc to reconsider the questions of law presented, upon certification for interlocutory appeal, concerning the applicability of § 8118 of the Defense Appropriations Act of 1987 to a contract between the Department of the Navy and the American Telephone and Telegraph Company. The Court of Federal Claims ruled that in view of the WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 3 EFTA00797877
Sivu 4 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999) failure of the Department of Defense to comply with § 8118, the contract, which had been performed, was void ab initio. We now hold that the contract was not void, and remand to the Court of Federal Claims for further proceedings in accordance with this premise. The Reduced Diameter Array Contract This contract arose in Cold War response to the new ultra-quiet Soviet submarines, which were difficult to monitor using available technology and equipment. Effective antisubmarine response requires that hostile submarines be reliably detected, classified, located, and tracked. The Navy, among its programs for this purpose, employed an integrated undersea acoustic sonar system called the Surveillance Towed—Array Sensor System (SURTASS). In SURTASS a suitably equipped surface vessel tows an array of undersea detection equipment through the ocean, while the equipment collects and transmits appropriate data for processing on shipboard and for transmission to shore-based facilities. The President's Annual Report *1370 to the Congress for fiscal 1987, on the topic of Antisubmarine Warfare Forces, referred to SURTASS as "[o]ne of our most important ongoing programs in this area." Id. at 188. On December 31, 1987, after competitive bidding, the Navy awarded AT & T a fixed price incentive fee contract for a subsystem of SURTASS, referred to as the Reduced Diameter Array. The contract was a "Total Package Procurement," requiring design of shipboard and shore-based electronics, ship-winch interface and tow cable, and an acoustic and electronic array some 8,000 feet long, to meet the new Soviet submarine capabilities. The contract required research, development, and the delivery and testing of an engineering development model, at a fixed ceiling price of $19,221,630, and included an option to the Navy to acquire a second engineering development model at a fixed ceiling price of $3,510,253, and an additional option to acquire three production- level models at a fixed ceiling price of $8,475,466. The contract was successfully performed by AT & T over a period of five years. With the price adjustments to which the Navy agreed during performance, the final fixed price was approximately $34.5 million. AT & T states that technical problems and unknowns arose throughout performance, and that its total cost was at least $91 million. The Navy rejected AT & T's requests for restructuring the contract and other relief, although AT & T directed attention to § 8118 of the Defense Appropriations Act and relevant Department of Defense policy directives concerning procurement of research and development for new technologies. WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 4 EFTA00797878
Sivu 5 / 27
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
AT & T duly brought suit in the
Court of Federal Claims under the
Contract Disputes Act. On cross
motions for summary judgment the
issues arising from the enactment of
§ 8118 were presented and argued.
The Court of Federal Claims ruled
that § 8118 applied to this contract,
that it had not been complied with
by the Department of Defense, and
that the contract consequently was void
ab initio. Responding to AT & T's
proposal that the appropriate remedy
was to reform the contract into the
cost-reimbursement form favored by
§ 8118, the Court of Federal Claims
held that since there had never been a
valid contract it could not be reformed.
The court held, however, that AT &
T was entitled to compensation for
its work on the basis of quantum
meruit, on a theory of implied-in-
fact contract. Before proceeding to
determine quantum, the court certified
for interlocutory appeal, in accordance
with 28 U.S.C. § 1292(d)(2), the
following questions:
(i) whether a contract executed in
violation of statutory restrictions on
the obligation and expenditure of
appropriated funds may be declared
void from the start at the instance of
the performing contractor, and, if so,
(ii)
whether
compensation
for
benefits
conferred
upon
the
Government (pursuant to the voided
contract) can be predicated on an
implied-in-fact contract with the
amount of recovery to be determined
pursuant
to
unjust
enrichment
principles.
A panel of the Federal Circuit, by split
decision, affirmed the ruling that the
contract was void ab initio. The court
also held that no relief was available
to AT & T on any theory, except
perhaps to replevin the goods that had
been delivered to the Navy. Upon the
petitions of both sides we have reheard
the matter en banc. I
Section 8118 of the Defense
Appropriations Act of 1987
Concern about the use of fixed price
contracts for research and development
*1371
phases
pervades
defense
procurement. In 1971 Department of
Defense Directive (DODD) 5000.1
stated that "[i]t is not possible to
determine the precise production cost
of a new complex defense system
before it is developed," and established
the policy of using cost-reimbursement
price terms for procurement of research
and
development.
The
Directive
stated: "Fixed price contracts are
normally not appropriate for research
and development phases." DODD
5000.1 & D.9.g (as amended, Sept.
1, 1987). The Federal Acquisitions
Regulations
governing
R
&
D
contracts also embodied this policy.
See, e.g., 48 C.F.R. § 35.006(c)
(1984-1998) ("Because the absence of
precise specifications and difficulties
in estimating costs with accuracy
(resulting in a lack of confidence in cost
estimates) normally precludes using
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works.
5
EFTA00797879
Sivu 6 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999) fixed-price contracting for R & D, the use of cost-reimbursement contracts is usually appropriate.") The record states that in the 1980s, despite these policy directives, the Navy returned to fixed price contracting for R & D as part of the Total Package Procurement concept. This in turn led to congressional investigations and hearings. An investigation conducted by the House Appropriations Committee concluded that for the development phases of new technologies, the Navy's use of fixed price contracting resulted in program delays, cost overruns, contractor claims, non- participation, and litigation. See Surveys & Investigations Staff, Report to the Comm. on Appropriations, U.S. House of Representatives: Navy Fixed Price Contracting in the Research, Development, Test and Evaluation (RDT & E) Account, 100th Cong., 1st Sess. (1987). The Report stated that: "Although Navy officials at the headquarters level have predicted immense success for the acquisition policy, the opinions expressed by Navy and other Service field procurement officials and technical experts indicated that [fixed price contracting] generally [has] proved unsuitable in an R & D environment." Id. at ii. The Report concluded that the nature of the work in research and exploratory development contracting "most frequently necessitates" use of the cost-reimbursement type contract. Id. at 11. At ensuing hearings on the 1988 Defense budget, concern was expressed about the continuing use of fixed price contracts for high-cost, high- risk development projects, as well as concern for meeting congressional oversight and allocation obligations under this form of procurement. Department of Defense Appropriations for 1988: Hearings Before the Defense Subcomm. of the Comm. on Appropriations, 100th Cong., 454- 55 (1987). Legislatively implementing these concerns, the House included in the Defense Appropriations Act of 1987 the provision that became § 8118: § 8118. None of the funds provided for the Department of Defense in this Act may be obligated or expended for fixed price-type contracts in excess of $10,000,000 for the development of a major system or subsystem unless the Under Secretary of Defense for Acquisition determines, in writing, that program risk has been reduced to the extent that realistic pricing can occur, and that the contract type permits an equitable and sensible allocation of program risk between the contracting parties: Provided, That the Under Secretary may not delegate this authority to any persons who hold a position in the Office of the Secretary of Defense below the level of Assistant Under Secretary of Defense: Provided further, That the Under Secretary WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 6 EFTA00797880
Sivu 7 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999) report to the Committees on Appropriations of the Senate and House of Representatives in writing, on a quarterly basis, *1372 the contracts which have obligated funds under such a fixed price-type developmental contract. Pub.L. No. 100-202, § 8118, 101 Stat. 1329, 1329-84 (Dec. 22, 1987). The accompanying Conference Report reiterated congressional concern that the risks of failure and of cost uncertainties be allocated equitably between government and contractor, and stressed the desire to "maintain the government's credibility as a reliable business partner." H.R. Conf. Rep. No. 100-498 at 623 (Dec. 22, 1987). Congress referred to the burden of a fixed price contract on the contractor when the miscalculation of development cost may have been that of the government agency as well as the contractor, and to the reluctance of some highly qualified firms to enter into such contracts. The Conference Report was unambiguous: "Fixed price contracts are normally not appropriate for research and development phases." Id. at 624. Thus Congress acted to adjust the risks of developing the advanced technologies needed in the service of national defense. Application of Section 8118 [lj Section 8118 prohibited the award of certain fixed price-type contracts unless the program risk was evaluated at a high level within the Defense Department, and required quarterly reports of such awards to the House and Senate Appropriations Committees. The government argues first that '8118 did not apply to the Reduced Diameter Array contract, thus eliminating any need for the Navy to have complied with the statute. The Court of Federal Claims correctly held otherwise. Section 8118 by its terms applies to "fixed price-type contracts in excess of $10,000,000 for the development of a major system or subsystem." The government argues that the Reduced Diameter Array is not a "major system," referring to a memorandum issued six weeks after enactment of § 8118 wherein the Under Secretary of Defense defined "major system" for the purposes of § 8118 as a system having a contract cost of over $75,000,000. In a Memorandum for Service Acquisition Executives, Directors of the Defense Agencies issued February 11, 1988, Under Secretary of Defense for Acquisition Costello instructed that "[t]he definition of major system at 10 U.S.C. § 2302(5) is the definition of that term for the purpose of [§ 8118]." This content was incorporated into SECNAV Instruction 4210.6A (April 13, 1988). 121 Section 2302(5) is a provision of chapter 137 of Subtitle A— General Military Law, which as then written defined "major system" as a system costing more than $75,000,000 WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. EFTA00797881
Sivu 8 / 27
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
for research, development, test, and
evaluation:
10 U.S.C. § 2302(5). The term "major
system" means a combination of
elements that will function together
to produce the capabilities required
to fulfill a mission need. The elements
may include hardware, equipment,
software or any combination thereof,
but excludes construction or other
improvements to real property. A
system shall be considered a major
system if (A) the Department of
Defense is responsible for the
system and the total expenditures
for research, development, test,
and evaluation for the system
are estimated to be more than
$75,000,000 (based on fiscal year
1980 constant dollars) or the eventual
total expenditure for procurement of
more than $300,000,000 (based on
fiscal year 1980 constant dollars)....
The government argues that the agency
had discretion to define the § 8118
"major system" in accordance with
'2302(5), and thereby to place a
$75,000,000 floor on the systems to
which § 8118 would apply. However, it
was not within the agency's discretion
to rewrite § 8118 to replace the statutory
threshold of $10,000,000 with that
of $75,000,000. Although an agency's
*1373 interpretation of a statute
it administers is indeed entitled to
deference, agency discretion does not
extend to changing a clearly stated
dollar figure. See Chevron, U.S.A., Inc.
v. Natural Resources Defense Council,
Inc., 467 U.S. 837, 842-43, 104 S.Ct.
2778, 81 L.Ed.2d 694 (1984) ("if the
intent of Congress is clear, that is the
end of the matter").
In addition, the AT & T contract
itself, and the Space and Naval
Warfare Systems Command's guide
to the SURTASS, described the
Reduced
Diameter
Array
as
a
"subsystem." Subsystems were not
defined in § 2305(5) and were not
mentioned in the Memorandum of the
Under Secretary. However, subsystems
costing more than $10,000,000 were
explicitly included in § 8118. Although
the government now argues that the
Under Secretary's Memorandum and
SECNAV Instr. 4210.6A really covered
a major system or a subsystem of
a major system, this interpretation is
contrary to the plain text of these
documents. It is apparent that the
Memorandum was contrary to the
statute, and in all events that it did not
include subsystems such as the Reduced
Diameter Array.
The government also argues that not
all of the funds expended under
the Reduced Diameter Array contract
were appropriated in the corresponding
Appropriations Act, and thus that
the § 8118 prohibition on obligating
or expending funds does not apply.
Indeed, the contract was structured
for multi-year incremental funding.
However, it is undisputed that the
starting research and development
effort drew on several millions of
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works.
8
EFTA00797882
Sivu 9 / 27
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
dollars of appropriated funds. The
multi-year funding does not excuse the
Defense Department from compliance
with § 8118.
Moreover,
contrary
to
the
government's argument, which is made
but not strongly pressed, this case does
not involve a funding deficiency or
implicate the Anti—Deficiency Act, 31
U.S.C. § 1341. See Hercules Inc. v.
United States, 516 U.S. 417, 427, 116
S.Ct. 981, 134 L.Ed.2d 47 (1996) ("The
Anti-Deficiency Act bars a federal
employee or agency from entering into
a contract for future payment of money
in advance of, or in excess of, an
existing appropriation."); see generally
Ferris v.
United States, 27 Ct.CI.
542, 546 (1892) ("An appropriation
per se merely imposes limitations
upon the Government's own agents ...
its insufficiency does not pay the
Government's debts, nor cancel its
obligations, nor defeat the rights of
other parties.") There is no issue in this
case of lack of appropriated funds.
We affirm the determination of the
Court of Federal Claims that §
8118 applies to this contract. The
government does not dispute that
the requirements of § 8118 were not
met by the Department of Defense.
There is no assertion that the Under
Secretary of Defense for Acquisitions
made or had made the program risk
and pricing determinations required
by § 8118, and no report of this
contract is stated to have been made to
the Senate and House Appropriations
Committees. Although the government
stresses that the contract was awarded
only nine days after the enactment of §
8118, this does not excuse the failure of
all compliance.
Consequences of Agency
Noncompliance With § 8118
PI We turn to the certified question
of the consequences of this failure
of compliance by the Department of
Defense. AT & T states that § 8118
was enacted at least in part for its
protection, and that the agency, by
failing to obey the law, can not deprive
AT & T of the protection of the
law. AT & T argues that § 8118
is a "mandatory statute" restricting
the agency's authority to obligate and
expend funds, and that the Navy's
direct contravention of § 8118 rendered
the Reduced Diameter Array contract
void ab initio.
The
government
responds
that
Congress chose and intended to enforce
§ 8118 *1374 through its oversight
powers, and that AT & T can not
benefit from whatever lapses may
have occurred within the Department
of Defense in its compliance with
congressional oversight legislation. The
government stresses that § 8118 did not
provide that these fixed price contracts
were prohibited, but only that the
Defense Department must review the
risk and its allocation at a specified
executive level, and must report to
Congress on a quarterly basis.
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works.
9
EFTA00797883
Sivu 10 / 27
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
14]
Legislative intent and precedent
both lead to the conclusion that the
AT & T contract was not void ab
initio as a consequence of the agency's
noncompliance. Invalidation of the
contract is not a necessary consequence
when a statute or regulation has been
contravened, but must be considered
in light of the statutory or regulatory
purpose, with recognition of the strong
policy of supporting the integrity of
contracts made by and with the United
States. In United States v. Mississippi
Valley Generating Co., 364 U.S. 520,
81 S.Ct. 294, 5 L.Ed.2d 268 (1961) the
Court explained that when a statute
"does not specifically provide for the
invalidation of contracts which are
made in violation of [its provisions]"
the court shall inquire "whether
the sanction of nonenforcement is
consistent with and
essential
to
effectuating the public policy embodied
in [the statute]." Id. at 563, 81
S.Ct. 294. Thus the policy underlying
the enactment must be considered
in determining the remedy for its
violation, when the statute itself does
not announce the sanction of contract
invalidity.
The policy embodied in § 8118
is elucidated in the congressional
response when § 8118 did not receive
full compliance from the Department of
Defense. See Alabama Rural Fire Ins.
Co. v. United States, 215 Ct.C1. 442, 572
F.2d 727, 733 (1978) ("illegality may
be proved with reference to legislative
history"). Congress simply tightened
the reporting provision, by moving
from after-the-fact quarterly reports
to before-award reports. Indeed, the
House version of § 8118 had initially
required before-award reports, but
this was dropped in Conference in
favor of the Senate version "to
reduce the appearance of congressional
micromanagement." H.R. Conf. Rep.
No. 100-498 at 623 (Dec. 22, 1987).
The Conference Report stated that if
Defense Department policy did not
become more uniform, "more severe
restrictions" would be imposed. Id. This
remark carries no hint of, and indeed
belies, an interpretation that § 8118 was
intended, upon enactment, to invalidate
any contract made without meeting
its internal review and reporting
requirements, for such a "restriction"
would already be extremely "severe."
The statutory shift to before-award
reports in succeeding years would be a
trivial discipline indeed, if meanwhile
all of the fixed price contracts within the
statutory scope, although in the process
of performance, or as in this case fully
performed, were void ab initio.
Only a few months after enactment
of § 8118 the House Appropriations
Committee
reported
that
the
"enforcement of existing policy in this
area has not yet been demonstrated,"
H.R.Rep. No. 100-681 at 147 (June 10,
1988), and recommended a pre-award
reporting requirement (which was
included in the enactment for the next
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works.
10
EFTA00797884
Sivu 11 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
fiscal year). The Senate Armed Services
Committee, considering this renewal,
stated explicitly that noncompliance
was not intended to be "the basis for
litigating the propriety of an otherwise
valid contract":
The committee recognizes that there
are circumstances in which fixed-
price development contracts are
appropriate (e.g., when costs and
foreseeable program risks can be
reasonably anticipated), and the
committee expects the Department to
establish clear guidelines under this
section for use of such contracts.
*1375 It is the intent of the
committee that this section be
applied in a manner that best serves
the government's interests in the long
term health of the defense industry,
and that this section not be used as
the basis for litigating the propriety of
an otherwise valid contract. Nothing
in this section shall be construed
to affect the requirements of section
8118 of the Department of Defense
Appropriations Act, 1988.
(Emphasis added.) S.Rep. No. 100-
326, 100th Cong., 2d Sess. at 105
(May 4, 1988). This explicit statement
of intent weighs heavily against
judicial invalidation of "an otherwise
valid contract," for the clearly stated
congressional purpose is contrary.
These congressional responses, made
with
knowledge of the agency's
imperfect compliance with § 8118,
negate any reasonable inference that
Congress intended simply to render
void
ab
initio,
even
after
full
performance, any fixed price contract
for which the Under Secretary's review
of risk allocation and the report to
the Committees were omitted. Congress
can not have intended to charge
the contracting partner with adverse
consequences depending on whether
the Defense Department carried out the
internal responsibilities and filed the
reports that Congress required.
Nor
is it
the judicial role to
discipline the agency's noncompliance
with the supervisory and reporting
instructions of congressional oversight.
See
Longshore
v.
United States,
77 F.3d 440, 443 (Fed.Cir.1996)
("Congress has undoubted capacity to
oversee the performance of Executive
Branch agencies, consistent with its
constitutional authority. It is not for
this court to instruct Congress on how
to oversee and manage its creations.");
E. Walters & Co. v. United States, 217
Ct.CI. 254, 576 F.2d 362, 367 (1978)
("The fact that a procurement practice
is prohibited does not necessarily mean
that it is therefore actionable. The
discipline to be administered in such
cases is a responsibility of the cognizant
procurement officials within the agency
[and not] by this court"); cf. National
Treasury Employees Union v. Campbell,
654 F.2d 784, 794 (D.C.Cir.1981)
(by statutory requirement that the
Comptroller General report on certain
expenditures "Congress itself is in a
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works.
11
EFTA00797885
Sivu 12 / 27
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999) position to monitor and enforce its spending limitations. It is not for us to question the effectiveness of existing remedies and infer additional remedies.") Both the DoD administration of § 8118, and the congressional response to this administration, make clear that Congress did not intend that this enactment would terminate fully performed contracts because of this flawed compliance. 151 Precedent reinforces our conclusion that the Reduced Diameter Array contract is not void ab initio. The invalidation of a contract after it has been fully performed is not favored. Precedent shows that those contracts that have been nullified, based on a failure to meet a statutory or regulatory requirement, are contracts that have not been substantially performed. E.g., Alabama Rural Fire Ins. Co. v. United States, 215 Ct.CI. 442, 572 F.2d 727, 733-34 (1978). In Prestex, Inc. v. United States, 162 Ct.CI. 620, 320 F.2d 367, 374-75 (1963), the court held a contract invalid, and refused to allow any recovery because no performance had occurred. It is not surprising that much of the litigation raising issues of violation of statute or regulation at the inception of government contracts has arisen in the bid protest context, where the asserted illegality has been explored before substantial performance has occurred. E.g., CACI, Inc. v. Stone, 990 F.2d 1233, 1235 (Fed.Cir.1993); Schoenbrod v. United States, 187 Ct.CI. 627, 410 F.2d 400, 403-04 (1969). We take incidental note that the case at bar also involved a disappointed bidder raising post-award objections, *1376 and that none of the objections were based on § 8118. In Harbor Gateway Commercial Property Owners' Ass'n v. United States Environmental Protection Agency, 167 F.3d 602 (D.C.Cir.1999), a case stressed in the dissenting opinion hereto, the court voided an EPA action because the Governor had not signed the request as the statute required. However, there was no issue of performance, or reliance, or any other contractual element. It is not before us to decide whether either party to the Reduced Diameter Array contract could have voided the contract early in its life and without penalty; the contract was performed for over five years, with no record suggestion from either party that because of § 8118 there was no contract. Judicial reluctance to annul performed contracts when the government did not comply with a statutory or regulatory requirement was explained by the Court of Claims in John Reiner & Co. v. United States, 163 Ct.CI. 381, 325 F.2d 438, 440 (1963), stating that "the court should ordinarily impose the binding stamp of nullity only when the illegality is plain." In Reiner the court recognized the "dilemma" of a contractor who becomes aware, while deep in the performance of a contract, of a possible WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 12 EFTA00797886
Sivu 13 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999) procurement illegality he did not cause: the contractor must either continue to perform a contract of uncertain validity, or discontinue performance and risk severe penalties if a court later disagrees with his assessment of the illegality. When a contract or a provision thereof is in violation of law but has been fully performed, the courts have variously sustained the contract, reformed it to correct the illegal term, or allowed recovery under an implied contract theory; the courts have not, however, simply declared the contract void ab initio. For example, in LaBarge Products v. West, 46 F.3d 1547, 1552-53 (Fed.Cir.1995) there was an illegal disclosure by the government during bidding; this court noted that the contract had been substantially performed and held that a valid contract existed despite the violation. In Beta Systems, Inc. v. United States, 838 F.2d 1179, 1185- 86 (Fed.Cir.1988) the court allowed reformation of the contract price term to correct a regulatory violation, stating that "[t]he risk of unintentional failure of a contract term to comply with a legal requirement does not fall solely on the contractor." In Urban Data Systems, Inc. v. United States, 699 F.2d 1147, 1154 (Fed.Cir.1983) the court held that a contract price term that was contrary to law did not invalidate the fully performed contract. In Trilon Educational Corp. v. United States, 217 Ct.C1. 266, 578 F.2d 1356, 1360 (1978) the court sustained a contract that was awarded after the contracting officer had negligently failed to meet a regulatory responsibility; the court held that the non-compliance with regulation was "a matter for internal resolution" and "did not render the resultant contract a nullity." In Clark v. United States, 95 U.S. 539, 542, 24 L.Ed. 518 (1877) the Court held a parol contract void for violation of the statute of frauds, but allowed recovery on an implied contract theory. The entirety of precedent strongly supports our conclusion that the Reduced Diameter Array contract is not void ab initio. Precedent does not favor the invalidation, based on governmental noncompliance with internal review and reporting procedures, of a contract that has been fully performed by either contracting party. 2 *1377 Although the parties discuss possible remedies, the issue of what relief may be available to AT & T is not before us, for the Court of Federal Claims did not consider AT & T's claims on the premise that the underlying contract was not void. We have not considered this issue, and express no view thereon. Answers to the Certified Questions For the reasons we have discussed, we conclude that the agency's failure to comply with the obligations of § 8118 WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 13 EFTA00797887
Sivu 14 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999) did not render the Reduced Diameter Array contract void ab initio. Any failure by the Department of Defense in its internal compliance with § 8118 can not be invoked, particularly after full contract performance, either to strip the Navy of authority to have entered into the contract or to bar AT & T from presenting such claims, if any, that it may have. The second certified question relates to remedy, but is based on the premise that the contract was void ab initio. Since that premise is incorrect, we do not reach the second certified question. Costs Each party shall bear its costs. QUESTIONS ANSWERED; CASE REMANDED. RADER, Circuit Judge, concurring in the result, in which MAYER, Chief Judge, and LOURIE, Circuit Judge, join. Because § 8118 of the Defense Appropriations Act does not apply to this contract, I concur. Section 8118 provides in relevant part: None of the funds provided for the Department of Defense in this Act may be obligated or expended for fixed- price-type contracts in excess of $10,000,000 for the development of a major system or subsystem.... (emphasis added). This particular section of the U.S.Code does not supply a definition of "major system." However, § 2302(5) of title 10 of the United States Code, which relates to government procurement contracts generally, defines "major system:" The term "major system" means a combination of elements that will function together to produce the capabilities required to fulfill a mission need.... A system shall be considered a major system if (A) the Department of Defense is responsible for the system and the total expenditures for research, development, test and evaluation for the system are estimated to be more than $75,000,000 ... or (C) the system is designated a "major system" by the head of WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 14 EFTA00797888
Sivu 15 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999) the agency responsible for the system. Therefore, the term "major system" refers to systems either with estimated costs above $75,000,000 or systems "designated a `major system' by the head of the agency responsible for the system." See 10 U.S.C. § 2302(5) (1986). Shortly after enactment of § 8118, both the Department of Defense and the Navy incorporated this statutory definition into their interpretation of that section. As the agency charged with interpretation and application of the statute, the Department of Defense's reasonable interpretation of § 8118 deserves deference. See Chevron U.S.A., Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837, 844, 104 S.Ct. 2778, 81 L.Ed.2d 694 (1984). The Department of Defense and Navy's interpretation alone gives meaning to all of the words in the statute. Both the Court *1378 of Federal Claims' interpretation and this court's interpretation in this opinion would render the "major system or subsystem" language superfluous and would invoke § 8118 for any fixed-price contract in excess of $10,000,000. This court chooses that course on the reasoning that the agency's interpretation "rewrite [s] § 8118 to replace the statutory threshold of $10,000,000 with that of $75,000,000." This reasoning, however, discounts the statute's alternative method of categorizing a project as a "major system," namely, designation by the head of the agency. Thus, a project beneath the $75,000,000 threshold of 10 U.S.C. § 2302(5) could nonetheless qualify as a "major system" upon designation by the head of the agency. This court's opinion discounts the reasonable reconciliations of the $10,000,000 contract amount requirement with the "major system" classification requirement. Under the agency's reasonable interpretation, the $10,000,000 contract amount requirement serves as a floor for invoking § 8118 in contracts involving a project designated as a "major system" by the department head. Furthermore, the $10,000,000 contract amount requirement does not lose its meaning for systems whose estimated costs exceed $75,000,000. Development of a major system typically requires multiple contracts with multiple developers. In these cases, the $10,000,000 requirement serves as a floor for application of § 8118 to each contract involved in the development of that "major system." Similarly, the $10,000,000 trigger amount excludes from § 8118 any subsystem contracts within a major system which do not satisfy this threshold amount. For these reasons, the $10,000,000 threshold continues to govern in conjunction with the $75,000,000 threshold for a "major system." In sum, these dual thresholds work together and provide a reasonable explanation for the agency's WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 15 EFTA00797889
Sivu 16 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999) interpretation of these statutes. Because reasonable, the agency's interpretation deserves deference. Even without deference to the Departments of Defense and Navy, their proposed interpretation of § 8118 alone gives meaning to all the statute's terms and should therefore govern this court's resolution. As noted above, this is the only interpretation which supplies meaning to all of the terms of the statute. Specifically, this is the only interpretation which gives meaning to the term "major system" as well as the $10,000,000 contract amount requirement. Finally, I read the term "subsystem" in § 8118 as linked to "major system" by its context within the statute. Although neither 10 U.S.C. § 2302(5), nor the interpretations of § 8118 proffered by the Department of the Defense or the Navy address the definition of "subsystem," the statute itself ties the definition of this term to the term "major system." In essence, this interpretation would apply § 8118 to "major systems and subsystems of major systems." This reading preserves the statute's "major system or subsystem" requirement rather than expanding application of § 8118 to all fixed-price-type contracts exceeding $10,000,000. Furthermore, to my eyes, this appeal does not present the question of whether this Reduced Diameter Array is a "subsystem" of a "major system." Although AT & T asserted below that the Reduced Diameter Array subsystem was a part of SURTASS, and that SURTASS was a major system according to the requirements of 10 U.S.C. § 2302(5), by consent of the parties before the Court of Federal Claims, that issue is not a subject of the certified appeal. For these reasons, I would not apply § 8118 to the Reduced Diameter Array contract at issue in this appeal. PLAGER, Circuit Judge, dissenting-in- part and concurring-in-part. I must respectfully dissent. The court refuses to honor an explicit mandate of an *1379 unequivocal Congressional enactment. "Legislative history" cannot justify that refusal.' A court has a responsibility to arrive at the right result in a case; it also has the obligation to explain itself in a manner that does no harm to the fabric of the law. Though the right result may eventually emerge, the route the court takes to get there has the potential for causing considerable harm to legal principles that I deem important. In the first part of its opinion, the court describes the Government's efforts over time to adjust the risks that are inherent in cutting-edge R & D contracts so that they are fair both to the Government and the contractor. See slip op. at 1369- 70. These efforts begin at least in 1971 with DODD 5000.1, and culminate, WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 16 EFTA00797890
Sivu 17 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
for purposes of this case, with the
enactment in 1987 of § 8118 as part
of that year's Department of Defense
("DoD") Appropriations Act. See id. at
1370-72. As the court explains, § 8118
prohibited using Government funds for
fixed price-type R & D contracts except
under certain conditions.
The court then sets out the history of the
R & D contract at issue in this case, and
concludes, correctly, that Section 8118
applies to this DoD fixed price-type
alleged contract. See id. at 1372-73. The
court concludes, again correctly, that
the exception provided in the statute,
permitting a fixed price-type R & D
contract under certain conditions, is not
applicable since the DoD did not take
the steps necessary to qualify for an
exception. See id.
This is the same conclusion on the
point reached by the Court of Federal
Claims, which this court now affirms.
The court rejects the Government's
various arguments to the contrary, and
finally concludes this part of its analysis
with the statement that: "Although the
government stresses that the contract
was awarded only nine days after the
enactment of § 8118, this does not
excuse the failure of all compliance." Id
Given that the court recognizes the
language of the Act to expressly
prohibit the use of Government funds
for such a contract, the obvious and
ineluctable conclusion would appear to
be that there was no contract, since
as a matter of law such contracts
were prohibited, and since there could
be no consideration offered for the
contractor's promised performance.
Remarkably, the court reaches exactly
the opposite conclusion, and finds
the contract valid, and presumably
enforceable. For the reasons I shall
explain, I cannot join the court in this.
1.
Omitting the inapplicable exception
language and its related provisos,
the operative words of the statute
are clear and to the point: "None
of the funds provided for the PoDI
in this [Appropriations' Act may be
obligated or expended for fixed price-
type contracts...." It is a rule of
constitutional law that, in absence of
an express appropriation, agencies may
not spend, and a fortiori cannot validly
contract to spend, any federal dollars.
See U.S. Const. art. I, § 9, cl. 7
("No Money shall be drawn from
the Treasury, but in Consequence of
Appropriations made by Law."). The
Supreme Court earlier reversed us when
in another context we failed to properly
apply that principle. See Office of
Personnel Management v. Richmond,
496 U.S. 414, 110 S.Ct. 2465, 110
L.Ed.2d 387 (1990).
Here, we do not have simply an
omission of authorization to expend;
we have an outright prohibition:
"None of the funds *1380 [otherwise
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works.
17
EFTA00797891
Sivu 18 / 27
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999) appropriated] may be expended ..." for the precise purpose for which the DoD contracted. Surely it should not be necessary for Congress to have added: "and we mean it," or perhaps, "and we mean it, and if you try, it won't be any good, so don't even bother." It is not uncommon for Congress to put prohibitions such as that contained in § 8118 in Acts appropriating funds to executive branch agencies.' A recent case in point: Congress, in an Appropriations Act which included the U.S. Environmental Protection Agency, 3 specified that "none of the funds made available under this heading may be used by the Environmental Protection Agency ... [for certain described activities affecting states] unless the Administrator receives a written request ... from the Governor of the State...." The EPA, on the basis of an authorizing letter from a state official, not the Governor, undertook such activity with regard to certain property in California. Affected interests appealed. Judge Sentelle, writing for the Court of Appeals for the District of Columbia Circuit, found that the state official's letter did not meet the terms of the statute, and readily concluded that, in the absence of a letter from the Governor himself, the EPA action was "null and void," and "was necessarily invalid." Harbor Gateway Commercial Property Owners' Ass'n v. United States Envtl. Protection Agency, 167 F.3d 602, 607 (D.C.Cir.1999). 4 In response to the Government's argument that EPA officials considered themselves to be in compliance, and in any event an invalidation of the action would require that the action be done again and would just cost the Government more money, the District of Columbia Circuit answered: We refuse to ignore the plain language of the Act in order to avoid potential costs which would not have arisen had EPA complied with the statute's language in the first instance. Indeed, when a statute's meaning is clear, and the enactment is within the constitutional authority of Congress, the "sole function of the courts is to enforce it according to its terms." Id. at 606 (emphasis added). That seems to be the law on the subject; I know of no cases to the contrary, and the court here cites none. WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 18 EFTA00797892
Sivu 19 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999) In this case, AT & T, after due negotiation with the Navy, offered to make and sell to the Navy for an agreed fixed price a submarine- detecting piece of equipment. The Navy accepted the offer, and proposed to pay for the work using funds from the 1987 Appropriations Act that contained the express prohibition set out above. As the Harbor Gateway court explained, the Navy's action was "null and void," and "necessarily invalid." Furthermore, the Navy's action in this case was taken for the purpose of entering into a contract. But the Navy was legally incapable of using Government funds unless it told Congress what it was up to in the manner required by the statute, which the Navy chose not to do. (It is difficult *1381 not to believe that both parties were fully aware of the statute and simply chose to ignore it, though that is of no moment to the issue before us. 5 ) Thus, not only was the act of contracting prohibited by statute, but as a matter of basic contract law no legally- binding contract could be created: offer, acceptance, and consideration remain a fundamental requirement for a legally-binding contract, whether between private parties or between a private party and the Government. See, e.g., Harbert/Lummus Agrifuels Projects v. United States, 142 F.3d 1429, 1434 (Fed.Cir.1998); Trauma Serv. Group v. United States, 104 F.3d 1321, 1325 (Fed.Cir.1997). Here, the Government could neither offer or pay consideration; no consideration, no contract, end of discussion, at least with respect to contract validity under basic contract principles. 2. I cannot agree with the court that the "purpose" of the statute overrides its express terms. The court tells us that this statute "must be considered in light of the statutory or regulatory purpose, with recognition of the strong policy of supporting the integrity of contracts made by and with the United States." Slip op. at 1374. Clearly, however, the purpose of this statute, expressed in no uncertain language, is exactly the opposite-it is intended to prevent contracts with the United States in contravention of its terms, not to support them. It has been some years since a court-invented "purpose" so blatantly repealed a Congressional enactment. Last century, in Rector, etc. of Holy Trinity Church v. United States, 143 U.S. 457, 471, 12 S.Ct. 511, 36 L.Ed. 226 (1892), the Supreme Court announced that this is a "Christian nation," and on that basis concluded that the purpose of a statute that banned immigration of foreign workers could not possibly be to prevent an English clergyman from coming to work in the United States. In this century, and certainly in recent WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 19 EFTA00797893
Sivu 20 / 27
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999) times, purpose-inventing by judges has received the opprobrium it deserves when used as an excuse for ignoring the law. Professor Dickerson, one of the early writers on statutory interpretation, described the process of purpose- inventing as if he had this case in mind: As with legislative intent, the danger in presuming an actual legislative purpose beyond what is expressly or impliedly revealed is that the interpreter will either attribute to the statute a purpose of his own contriving or search for actual purpose so relentlessly that he goes beyond the limits of the appropriate available evidence. Reed Dickerson, The Interpretation and Application of Statutes 92 (1975). Writing more formally for the Court a half-century ago, Justice Jackson said, "we take the Act as Congress gave it to us, without attempting to conform it to any notions of what Congress would have done if the circumstances of this case had been put before it." Western Union TeL Co. v. Lenroot, 323 U.S. 490, 501, 65 S.Ct. 335, 89 L.Ed. 414 (1945). In the same vein, and more recently, the Supreme Court, Justice Scalia writing, said, "Courts may not create their own limitations on legislation, no matter how alluring the policy arguments for doing so,...." Brogan v. United States, 522 U.S. 398, 118 S.Ct. 805, 811-12,139 L.Ed.2d 830 (1998). In support of its position, the court cites various pieces of what it describes as legislative history. However, a prerequisite to judicial use of legislative history, even relevant legislative history, is a finding that *1382 the statute at issue is ambiguous. "Our first step in interpreting a statute is to determine whether the language at issue has a plain and unambiguous meaning with regard to the particular dispute in the case. Our inquiry must cease if the statutory language is unambiguous and `the statutory scheme is coherent and consistent.' " Robinson v. Shell Oil Co., 519 U.S. 337, 117 S.Ct. 843, 136 L.Ed.2d 808 (1997) (Justice Thomas, writing for a unanimous Court) (quoting United States v. Ron Pair Enters., Inc., 489 U.S. 235, 240, 109 S.Ct. 1026, 103 L.Ed.2d 290 (1989)). To the court's credit here, the majority does not pretend to find in this unequivocal statute any ambiguity. Rather, it simply concludes that committee report language, nowhere addressed to the specific problem before us, trumps statutory clarity. 6 WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 20 EFTA00797894
Sivut 1–20 / 27